The President of the Republic, Nana Addo Dankwa Akufo-Addo, has expressed great satisfaction with the progress of work ongoing on the reconstruction and modernization of the Maternity and Children’s block of the Komfo Anokye Teaching Hospital, in Kumasi.

Inspecting the project on Monday, 17th October 2022, as part of his four-day working visit to the Ashanti region, the President was informed that the project, thus far, has seen a 100% demolition of the old structure, with the current progress of work about 60 percent complete.

It will be recalled on Friday, 15th May 2020, the President cut the sod for the re-activation of work on the Maternity and Children’s ward at the teaching hospital after over four decades of neglect.

Before this, the Akufo-Addo government, represented by the Ministry of Health had on 6th November 2019, employed Contracta Construction UK Limited for the design, execution and completion of works and the remedying of any defects, which include the re-modeling and completing of shell spaces for the existing building structure.

Subsequently, after the Contractor’s structural integrity report for the existing building structure, the Government decided to revise the scope of works in November 2020 to include the complete demolition of the old existing structure, and a re-design, construction and complete equipping of the new and modern mother and child health facility

The revised contract also includes the provision of a 3-year maintenance program for medical equipment with training and technical assistance, procurement of medical and non–medical consumables, and the training of needed human resource training, technical assistance and mentorship programs.

The new design has 8 floors, 22 consulting rooms, 3 group consulting rooms, 2 consulting rooms for adult emergencies, 2 consulting rooms for Paediatric Emergencies, 3 Auditorium (45 seats, 43 seats and 145 seats), 5 seminar rooms (14 seats) and 506 Beds with the capacity to hold, 199 pediatric cots, 136 Paediatric beds, 19 birthing beds and 152 Adult beds.

Additionally, the block will also have 1 Obstetrics Theater, 7 General theatres, Pharmacy, Dispensaries, Laboratories as well as Ancillary spaces.

Once completed, it will house an intensive care unit, a high-dependency unit, isolation rooms and student lecture halls, with the capacity to provide catering services for staff, patients and students.

The expanded works have also resulted in the ongoing reconstruction of the Station Basic School classroom block at the UDDARA Barracks, which is scheduled to be completed by January 2023.

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

Bagbin Constitutes Nine-Member Committee To Probe UniBank, UT Bank Collapse

The Speaker of Parliament, Alban Bagbin, has constituted a nine-member committee to…

Support Gov’t To Make Ghana A Mining Investment Hub – Samuel A. Jinapor

The Minister for Lands and Natural Resources, Hon. Samuel A. Jinapor(MP) has…

We Will Make The World Know Allegations Levelled Against GES Not True- Bonaventure

Most Rev.John Bonaventure Kwofie, Catholic Metropolitan Archbishop of Accra has disclosed to…

PARLIAMENT APPROVES KEN OFORI-ATTA AS FINANCE MINISTER

Parliament of Ghana has today given an approval to Mr Ken Ofori-Atta…